Skip to content

Find today's releases at new Decisions Search

opener
114039

Hilton Plaster Co. v. Knoblauch

View PDFPDF icon linkimg description
  • Status Unpublished
  • Release Date
  • Court Court of Appeals
  • PDF 114039
1

NOT DESIGNATED FOR PUBLICATION

No. 114,039

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

HILTON PLASTER COMPANY, INC.,
Appellee,

v.

ROBERT L. KNOBLAUCH A/K/A BOBBY KNOBLAUCH,
and
WHEATLAND DRYWALL, INC.,
Appellants.


MEMORANDUM OPINION

Appeal from Sedgwick District Court; DOUGLAS R. ROTH, judge. Opinion filed September 30,
2016. Affirmed.

James T. McIntyre, of Law Offices of James T. McIntyre, of Wichita, for appellant.

Keith D. Richey, of Law Office of Keith D. Richey, of Wichita, for appellee.

Before PIERRON, P.J., GREEN and BUSER, JJ.

Per Curiam: Wheatland Drywall (Wheatland) was hired as a subcontractor to do
construction work. Wheatland contacted Hilton Plaster (Hilton) to do stonework on the
same project. When Hilton was not paid, it sued Wheatland and its owner, Bobby
Knoblauch. Wheatland and Knoblauch alleged that the general contractor had hired
Hilton. Knoblauch eventually learned that the general contractor had paid Wheatland for
work that Hilton had completed, but Wheatland and Knoblauch maintained that they did
not hire Hilton as a subcontractor. The trial court ruled that Wheatland had hired Hilton
to do stonework. On appeal, Wheatland and Knoblauch challenge the trial court's ruling,
2

which served as the basis for the award of a statutory interest rate and attorney fees.
Determining that substantial support existed for the trial court's factual finding, we
affirm.

In 2012, Wheatland entered into a subcontractor agreement with Flynn
Construction Management General Contracting, Inc. (Flynn). Flynn had been hired as a
general contractor to build a Planet Fitness in Wichita, Kansas. Wheatland was hired as a
subcontractor to perform framing and drywall. The owner of Wheatland, Bobby
Knoblauch, later e-mailed Flynn's president with estimates for the additional services of
Exterior Insulation and Finish System (EIFS), additional framing, and stonework, quoting
a price of $12,800 for the stonework. The contract was revised to include EIFS and
framing for the price of $35,100 that Knoblauch had quoted. In fact, the contract was
revised a total of seven times. Contract Revision 5 lists stonework at a price of $12,350.
Unlike the first four revisions, Contract Revisions 5 through 7 were not signed by
Knoblauch.

But Hilton—not Wheatland—performed the stonework on the Planet Fitness
project. It sent Wheatland an invoice for the work with the price listed as $12,330. When
Wheatland failed to pay, Hilton sued, naming both Wheatland and Knoblauch as
defendants. Hilton's petition alleged that Wheatland and Knoblauch had hired it as a
subcontractor. The petition also alleged that according to the Kansas Fairness in Private
Construction Contract Act, K.S.A. 16-1801 et seq., Hilton was entitled to interest on the
unpaid amount at a rate of 18% per annum and also costs and attorney fees. Wheatland
and Knoblauch, in their answer, denied that they had hired Hilton as a subcontractor.
They also claimed that in any communication about the project with Hilton, Knoblauch
was acting as a disclosed agent of Flynn and that Hilton was Flynn's subcontractor.

After Wheatland and Knoblauch failed to respond to discovery requests, Hilton
moved to compel discovery and for sanctions. The trial court granted the motion,
3

ordering Wheatland and Knoblauch to respond to Hilton's discovery requests and pay
$500 in sanctions. They did respond to the discovery requests, but they evidently failed to
turn over several of the documents that Hilton had requested. Included in those
documents was a series of e-mails from Flynn to Knoblauch that Hilton's attorney had
previously received from Flynn. In the e-mails, Flynn directed Knoblauch to pay Hilton
and threatened to press charges for falsifying an affidavit. Knoblauch apparently never
responded to any of the e-mails. Wheatland and Knoblauch also never turned over its
bank records or Contract Revisions 5 through 7. Hilton moved a second time to compel
discovery and for sanctions.

The trial court held a hearing on the motion and recessed until a later date to allow
the parties time to obtain and review Wheatland's bank records, which the trial court had
ordered the bank to produce. At the next hearing, Hilton stated that the bank records and
the documents from Flynn were sufficient to prove that Wheatland had failed to produce
documents that Hilton had requested and that it had received payment from Flynn for
work that Hilton had completed. The parties agreed that the case should be set for an
evidentiary hearing. The trial court ordered both Knoblauch and David Hilton (David),
the owner of Hilton Plaster, to personally appear.

One day before the evidentiary hearing, Hilton's attorney received a letter from
Wheatland and Knoblauch's attorney, stating:

"Mr. Knoblauch has finally acknowledged to me after extensive review of the
records you provided, that he did in fact receive $12,350 of money that should have gone
to Hilton Plaster. I am therefore willing to agree to Entry of Judgement in the amount of
$12,350, interest at a rate to be determined by the court, from June 2013 until paid, and
for the court to determine the amount of attorney fees due."

The trial court read the letter into the record at the hearing. Wheatland and Knoblauch
objected to the application of the statutory interest rate and the awarding of costs and
4

attorney fees, arguing that the Kansas Fairness in Private Construction Contract Act did
not apply because Hilton was not their subcontractor. The trial court then heard testimony
from both Knoblauch and David.

Knoblauch testified that he had only recently realized that Wheatland had been
overpaid and that he had not seen Contract Revision 5, which listed the stonework, until
recently at his attorney's office. He also testified that there were no e-mails exchanged
between David and him; that Wheatland and Hilton did not have a contract; and that he
did not interpret Hilton as being a part of the contract with Flynn. On cross-examination,
Knoblauch stated that Flynn's president directed him to seek bids for the stonework and
that Hilton's bid was one of three. Further, he did not have any of the e-mails from Flynn
because he had deleted them and he had not kept records from any of his jobs. Moreover,
contrary to those e-mails, Knoblauch claimed that he had responded to Flynn's president
about the issue. Although he was not aware of anyone else having contact with Hilton,
Knoblauch stated that he had nothing to do with Hilton's work and had not even inspected
the completed project. Finally, when David called asking for payment, Knoblauch told
him to contact Flynn because he had nothing to do with Hilton.

According to David, Knoblauch first asked him over the phone to give a quote on
stonework. David maintained that he had no contact with Flynn, or anyone else, and that
all his contact was with Knoblauch. David also testified that Knoblauch visited the
jobsite, speaking with Hilton employees, and that when the stone ran out, he contacted
Knoblauch to obtain more. He had not dealt with nor did he have conversations with
anyone else. According to David's understanding, Knoblauch had hired Hilton. David
also stated that when he called Knoblauch about getting paid, Knoblauch initially said
there was a dispute over the square footage but then stopped taking his calls.

After considering the credibility of the witnesses, the trial court found that Flynn
had hired Wheatland as a subcontractor and that Wheatland had invited others, including
5

Hilton, to bid on the stonework. The court also specifically found that Wheatland was not
acting as Flynn's agent but was a subcontractor that hired another subcontractor, Hilton,
and was paid for work that Hilton had performed. The trial court also noted that
Knoblauch's failure to keep good records and his failure to realize that Flynn had
overpaid Wheatland was not a defense to Wheatland's failure to pay Hilton for stonework
it had completed. Finally, the trial court determined that the Kansas Fairness in Private
Construction Contract Act statutory interest rate applied and awarded attorney fees to
Hilton.

Was the Trial Court's Finding That Wheatland and Knoblauch Hired Hilton as a
Subcontractor Supported by Substantial Competent Evidence?

Wheatland and Knoblauch maintain that because substantial competent evidence
did not support the trial court's finding that Wheatland hired Hilton as a subcontractor,
the trial court erred in awarding Hilton attorney fees and applying the statutory interest
rate. In their brief, they seem to suggest that the trial court erred in interpreting or
applying the Kansas Fairness in Private Construction Contract Act. There is no dispute
that both Wheatland and Hilton were subcontractors. The remaining issue is whether they
were both subcontractors for Flynn or whether Wheatland had hired Hilton as a
subcontractor.

When reviewing a trial court's factual findings, an appellate court generally applies
a substantial competent evidence standard. Hamel v. Hamel, 296 Kan. 1060, 1078, 299
P.3d 278 (2013). Substantial evidence is evidence that "a reasonable person might accept
as sufficient to support a conclusion." Owen Lumber Co. v. Chartrand, 283 Kan. 911,
916, 157 P.3d 1109 (2007). An appellate court ignores conflicting evidence and other
inferences that could be drawn from the evidence which do not tend to support the district
court's findings. Unruh v. Purina Mills, 289 Kan. 1185, 1196, 221 P.3d 1130 (2009). To
6

the extent that statutory interpretation is necessary, an appellate court's review is
unlimited. Neighbor v. Westar Energy, Inc., 301 Kan. 916, 918, 349 P.3d 469 (2015).

K.S.A. 2015 Supp. 16-1803(g) states: "If the contractor fails to pay a
subcontractor within seven business days, the contractor shall pay interest to the
subcontractor beginning on the eighth business day after receipt of payment by the
contractor, computed at the rate of 18% per annum on the undisputed amount." That
section also applies to subcontractors and their subcontractors. K.S.A. 2015 Supp. 16-
1803(h). A subcontractor is defined as "any person performing construction covered by a
contract between an owner and a contractor but not having a contract with the owner."
K.S.A. 2015 Supp. 16-1802(h). Contractors are persons "performing construction and
having a contract with an owner of the real property or with a trustee, agent or spouse of
an owner." K.S.A. 2015 Supp. 16-1802(d). Also, the prevailing party in an action under
K.S.A. 2015 Supp. 16-1803 is entitled to costs and reasonable attorney fees. K.S.A. 16-
1806.

David testified that Knoblauch initially contacted him over the phone and asked
him for a quote. After some time, Knoblauch contacted David again and asked if he was
still interested in doing the job. Hilton then began doing the stonework. David also
testified that he had no contact with Flynn, all contact was through Knoblauch, and that
he did not have any other contact about the job with anyone else. According to David's
testimony, Knoblauch also visited the jobsite and spoke with Hilton employees, and when
the workers ran out of stone, David called Knoblauch, who then ordered more. Finally,
David testified that he had not dealt with anyone except for Knoblauch. He did not know
of Flynn's involvement; from his understanding, Knoblauch had hired Hilton to do the
stonework; and he did not have any conversations about the project with anyone else.

Wheatland and Knoblauch argue that the contract revision showing the stonework
was not signed by Knoblauch and that no documentary evidence showing that Wheatland
7

had hired Hilton as a subcontractor was presented. But as previously mentioned, when
reviewing a trial court's factual findings, this court ignores any conflicting evidence.
Unruh, 289 Kan. at 1196. Further, although no documentary evidence was presented,
David's testimony, as shown, supported the trial court's finding that Wheatland had hired
Hilton as a subcontractor. In making that finding, the trial court, as it specifically noted,
determined the credibility of Knoblauch and David. Moreover, appellate courts do not
redetermine the credibility of witnesses. See Garvey Elevators, Inc. v. Kansas Human
Rights Comm'n, 265 Kan. 484, 496-97, 961 P.2d 696 (1998).

Because a reasonable person would accept David's testimony as sufficient to
support the trial court's conclusion that Wheatland had hired Hilton as a subcontractor,
the trial court's factual findings were supported by substantial competent evidence. Thus,
the trial court properly awarded Hilton attorney fees and applied the statutory interest
rate.

Affirmed.
Kansas District Map

Find a District Court